BASELINE SCHEDULE:
ID,Name,Baseline_Duration,Baseline_Start,Baseline_Finish
1,Project Start,0 days,01-01-25,01-01-25
2,Project Start Mobilization,7 days,01-01-25,09-01-25
3,Earth Works,34 days,16-06-25,31-07-25
4,Concrete Skeleton Works,185 days,30-06-25,13-03-26
5,Plumbing Water Supply First Fix,32 days,22-09-25,04-11-25
6,Plumbing Drainage First Fix,29 days,06-10-25,13-11-25
7,Exterior Walls Installation,115 days,20-10-25,27-03-26
8,Waterproofing for Wet Areas,18 days,03-11-25,26-11-25
9,Exterior Plastering Works,78 days,15-12-25,01-04-26
10,Interior Walls Installation,55 days,27-11-25,11-02-26
11,Electrical Wiring First Fix,25 days,11-12-25,14-01-26
12,Doors and Windows Installation,68 days,24-12-25,27-03-26
13,Ceramic Tile Works,110 days,12-02-26,15-07-26
14,Elevator Installation,39 days,16-03-26,07-05-26
15,Interior Plastering Works,19 days,16-01-26,11-02-26
16,Painting Works,53 days,16-07-26,28-09-26
17,Plumbing Second Fix,20 days,29-09-26,26-10-26
18,Electrical Wiring Second Fix,24 days,29-09-26,30-10-26
19,Heating System Second Fix,38 days,29-09-26,19-11-26
20,Project End,0 days,19-11-26,19-11-26

AS-BUILT SCHEDULE (with delay notes):
ID,Name,Baseline_Duration,Baseline_Start,Baseline_Finish,Duration,Start_Date,Finish_Date,Notes,Percent_Complete
1,Project Start,0 days,01-01-25,01-01-25,0 days,01-01-25,01-01-25,,100%
2,Project Start Mobilization,7 days,01-01-25,09-01-25,12 days,01-01-25,16-01-25,"Increased duration from 7 to 12 days. Delay due to client not having the site facilities ready for mobilization",100%
3,Earth Works,34 days,16-06-25,31-07-25,25 days,16-06-25,18-07-25,"Earth works duration reduced from 34 to 25 days. 9 days savings due to better than expected weather",100%
4,Concrete Skeleton Works,185 days,30-06-25,13-03-26,220 days,30-06-25,01-05-26,"Duration exceeded by around 6 weeks (35 days) due to delays in delivery of Rebars and multiple delays of on site conditions, inspections, etc.",61%
5,Plumbing Water Supply First Fix,32 days,22-09-25,04-11-25,32 days,22-09-25,04-11-25,,100%
6,Plumbing Drainage First Fix,29 days,06-10-25,13-11-25,29 days,06-10-25,13-11-25,,100%
7,Exterior Walls Installation,115 days,20-10-25,27-03-26,115 days,20-10-25,27-03-26,,47%
8,Waterproofing for Wet Areas,18 days,03-11-25,26-11-25,18 days,01-12-25,24-12-25,"waterproofing started around 3 weeks later per the delay in the concrete skeleton works",100%
9,Exterior Plastering Works,78 days,15-12-25,01-04-26,78 days,15-12-25,01-04-26,,18%
10,Interior Walls Installation,55 days,27-11-25,11-02-26,55 days,25-12-25,11-03-26,,11%
11,Electrical Wiring First Fix,25 days,11-12-25,14-01-26,25 days,08-01-26,11-02-26,,0%
12,Doors and Windows Installation,68 days,24-12-25,27-03-26,120 days,24-11-25,08-05-26,"duration changed from 68 to 120 days. Main reason is designer and client requested new types of doors to be installed which prompted a redesign",24%
13,Ceramic Tile Works,110 days,12-02-26,15-07-26,132 days,12-03-26,11-09-26,"Activity was on hold for 18 days due to material delivery problems",0%
14,Elevator Installation,39 days,16-03-26,07-05-26,39 days,04-05-26,25-06-26,,0%
15,Interior Plastering Works,19 days,16-01-26,11-02-26,19 days,13-02-26,11-03-26,,0%
16,Painting Works,53 days,16-07-26,28-09-26,40 days,14-09-26,06-11-26,"Painting works took only 40 days instead of 53 days due to better than expected summer weather",0%
17,Plumbing Second Fix,20 days,29-09-26,26-10-26,15 days,09-11-26,27-11-26,"Duration reduced because of client pressure to handover. Crashing Recovery",0%
18,Electrical Wiring Second Fix,24 days,29-09-26,30-10-26,20 days,09-11-26,04-12-26,"Duration reduced because of client pressure to handover. Crashing Recovery",0%
19,Heating System Second Fix,38 days,29-09-26,19-11-26,30 days,09-11-26,18-12-26,"Duration reduced because of client pressure to handover. Crashing Recovery",0%
20,Project End,0 days,19-11-26,19-11-26,0 days,18-12-26,18-12-26,,0%
